Median months on site, across the segments each country publishes. Build-out periods and portfolio figures are excluded: they measure a development, not a dwelling, and mixing them inflates a country by a decade.
Median months from application to decision. Several of these are statutory deadlines rather than observed durations, which is the comparability warning the study makes at length — a deadline is a promise, not a measurement.
A 38-country scope is true of the ambition and not of the measurements. These two proportions are the study’s most important finding and the reason it is a study about publication rather than about building.
Records with a construction figure — 26 of 38 countries have one at all
Records with all three phases — and every one of them splices two publishers, two years, or a deadline
Comparative research · 38 countries
A source-anchored comparison of how long it takes to deliver a home in 38 countries — separating the time spent getting permission, the time spent waiting after permission, and the time actually spent building.
The headline finding of this study is about measurement, not construction. Not one of the 38 countries examined publishes all three phases of housing delivery as a regular statistical series. Most publish one phase well, one badly, and one not at all — and which phase they choose to measure turns out to correlate with which phase they are good at.
Countries with fast permitting publish permitting statistics. New Zealand reports a median building-consent decision in 13 working days, quarterly, by authority. Denmark publishes municipal case-handling times for 30,288 cases a year. Neither publishes how long it takes to build the house. Conversely, the United States measures construction to within a tenth of a month across a million homes a year and does not collect the date a permit application was filed — anywhere, at any level of government.
5.0
months to build a detached house in Japan — the fastest measured construction phase in the study
51.0
months to build a detached house in Poland, where 75% of them are owner-built
8.1
months the median Dutch home now waits between permit granted and ground broken — up from 5.0 in 2015
0 of 38
countries publishing approval, waiting and construction time as a regular series
Every figure in this study is assigned to one of three phases, and never blended without a label:
The separation is not pedantry. It is the whole finding. In the Netherlands — which has the best-decomposed housing data in the world, a full register count rather than a survey — the median new dwelling in 2025 spent 8.1 months waiting after its permit was granted and 13.3 months being built. Ten years earlier those numbers were 5.0 and 9.4. The waiting grew 62%; the building grew 41%. And critically, that 8.1-month wait sits entirely downstream of the Dutch statutory permit deadline, so no amount of permit-office reform touches it.
The building itself: construction phase only
Ground-breaking to completion, in months. Only the countries that publish or permit derivation of a construction duration — about a dozen of the 38 — can appear here. Hover any bar for the statistic type and source.
Read that chart carefully, because its most interesting row inverts the expected order. In Poland, single-family houses take twice as long to build as apartment blocks — 51.0 months against 24.8. Poland's statistical office is one of the few in the world that publishes construction duration split by who commissioned the work, and the split explains it: developer-built housing takes 24.9 months, owner-built housing takes 59.1 months. The same office publishes the same split by construction technology, and the technology barely matters. Using identical monolithic construction, self-builders take 47.8 months and developers take 24.5. The binding constraint is not the method. It is the client's cash flow.
That pattern recurs everywhere the data can see it. In the United States, an owner-built house takes 12.8 months of construction against 6.1 for a builder's spec home — a 2.1× ratio inside one country, wider than the gap between the United States and most of its comparators. In Lagos, where roughly 90% of housing is self-built and mortgage lending is about 0.5% of GDP, the median self-build takes 41.7 months and the mean takes 48.3. The gap between that median and that mean is the signature of a build financed out of savings: foundation, then blockwork, then roof, then finishes, with months of nothing in between.
Where the time actually goes
The eight countries and segments where the delivery period can be decomposed. Note how much of each bar is neither approval nor construction — it is a permitted project with nobody on site.
A single global ranking is not available, and the reason matters: only about a dozen of the 38 countries publish a construction duration at all. The ranking below covers those that do, and states the statistic type each time, because construction duration is right-skewed and a mean will always exceed a median.
Here the spread is not a factor of ten. It is a factor of forty, and the extremes are worth stating precisely.
Fastest: Japan at roughly 10 months from signing a building contract to completion; Australia at 11.5 months from approval to completion for a detached house; the United States at 8.8 months from permit issuance — though the American figure excludes an approval phase that nobody measures, so it is not a true P3 and should not be presented as one.
Slowest: Chile at 65.7 months from first drawing to final reception, up from 42.6 in 2018 — a 54% deterioration in seven years. Israel at roughly 46–51 months. Singapore's public housing programme at 51.6 months at its COVID peak, since recovered to a 36–48 month target. And England, where the median large housing site takes 5.2 to 6.3 years from planning application to its first completed home, and where the Letwin Review found a median build-out period of 15.5 years for the site as a whole. The honest English answer is that the house takes months, the site takes fifteen years, and which number you quote depends on whether you are the builder or the person waiting for the nine-hundredth home.
What drives the spread. Four factors do most of the work, and construction method is the weakest of them.
Client type is the strongest single predictor. Poland's 2.4× self-build penalty survives every technology control. The US spec-vs-owner-built ratio is 2.1×. Any national “average” that mixes them is close to meaningless.
Building type is second. Apartments take roughly twice as long as houses almost everywhere the data splits them: Netherlands 17.9 vs 10.3, United States 16.5 vs 7.4, Australia 26.6 vs 8.7. Within apartments, duration scales with size — US buildings of 2–4 units take 12.7 months, 20+ units take 19.1.
Regulatory regime is third, and it acts mostly on P1 and the idle gap rather than on construction.
Construction method is fourth and consistently over-claimed. Singapore's BCA — which mandates volumetric modular construction on selected government land-sales sites — quantifies the saving at 1 to 2 months on a 36–48 month apartment cycle, a 2–5% reduction. Scotland builds 90–95% of its new homes in timber frame and still runs a 44-week mean wait for major housing permission. Timber frame reaches watertight in 2–3 weeks against 8–12 for masonry, but that saving lands inside a programme dominated by groundworks, services and finishes — and it does nothing at all to the approval phase, which is where the years actually go.
In several countries the paperwork is longer than the building. This is the finding worth carrying away, and it is well evidenced in five places.
England. The mean time to determine an outline planning application for major housing reached 710 days in 2024, against 284 days in 2014 — an increase of 426 days, or 150%, both as Lichfields publishes them. Only 4% of 2024 applications were decided inside the statutory 13 weeks; 64% took more than a year. Two details make this worse than it sounds. Approvals take longer than refusals (857 days against 453) — the delay is concentrated in getting to yes. And it is now roughly six months quicker on average to be determined on appeal than by the local authority, an inversion that says something stark about local planning capacity. Meanwhile England's official statistic reports that 91% of major applications were decided “within 13 weeks or the agreed time,” a figure rendered almost meaningless by the fact that 77% of those applications carry a negotiated extension.
Chile. The clearest documented case anywhere. Total elapsed time rose 703 days — 54% — in seven years. Chile has the shortest statutory permit deadline in this study (30 calendar days, 15 with an independent reviewer) and the longest observed permit stage (223 days for the building permit alone, 372 for the full pre-construction sequence). That is 7.4× the legal ceiling. The spread between municipalities in one metropolitan area is 2.7×: Renca 311 days, Conchalí 837. Chile's own national productivity commission mapped 439 permitting procedures across 71 public entities, 63 of them capable of stopping a project outright, and found four agencies holding 5,517 pending applications out of 8,881 submitted. Permit processing time is estimated at roughly 12% of a housing unit's value.
Spain. No municipality in the Community of Madrid meets the three-month legal maximum. The capital averages 11.0 months; Las Rozas averages 21.1. The developers' association that compiled the figures put it plainly: licence times are “in many cases longer than the construction of the building itself.”
Israel. Mean permit issuance of 319 days across all tracks, rising to 407 days where a relaxation or non-conforming use is involved — against a World Bank benchmark of 114 days that Israel's own State Comptroller cites. The Comptroller found that in six of eight committees audited, the 2014 licensing reform produced no real shortening at all.
Canada. Municipal planning approval for multi-unit housing averages 11.2 months nationally — independently corroborated by CMHC's own estimate of “on average, a full year” — with a 15× spread from Saskatoon's 2.0 months to Hamilton's 31.0. Add a high-rise permit-to-start gap of 9 to 15 months and Canadian apartment delivery is dominated by waiting, not building.
Two countries have driven the approval phase close to zero, by opposite routes.
Saudi Arabia outsourced the review. Its Balady platform publishes a service-level agreement of 1 to 10 days for a building permit, while the ministry's own service card says “immediately.” Both are true and the difference is the finding: substantive review — including Saudi Building Code compliance — has been moved out of government entirely, to accredited private engineering offices and technical inspection companies that carry liability, backed by mandatory latent-defects insurance. The government's residual step is a payment gate, and it is genuinely instant, because the government is no longer doing the reviewing. In 2019 the same permit took 19 days.
Dubai is automating it. On 9 August 2026 — eight days before this study was compiled — Dubai Municipality announced an AI system that issues villa building permits automatically, verifying plot requirements, checking architectural designs against the Dubai Building Code, assessing MEP systems and validating structural safety. Full rollout is scheduled 26 weeks out, around February 2027. Abu Dhabi reports its own platform has cut residential villa permit processing 57%.
Japan offers the closest thing to a natural experiment. Since 1999 its building-confirmation checks — a conformance verification, not a discretionary approval — can be performed either by municipal officials or by competing private certification bodies. On the routine wooden two-storey class, under the identical statute and the identical 35-day ceiling, private bodies average 10 days where public officials average 35. On that class the variance is administrative throughput, not rule ambiguity. The honest qualifier is that the advantage is not universal: on the class that requires a full structural conformity review, the ordering has just reversed — in the current financial year private bodies are averaging 38 days against the public officials’ 34, having been 35 against 62 the year before. Private review wins decisively on routine work and is roughly at parity on hard work. And Japan is still only at about 56% electronic submission: the rules are already largely deterministic, the pipeline is not yet automated.
Several of the numbers above cannot be placed in one column without qualification. These are the material ones.
Construction duration is right-skewed, so this matters more than it sounds. Germany, Poland, Israel, Canada, Australia and the United States publish means only for construction duration. The Netherlands is the only country in this study that publishes a construction-duration median — and it publishes both statistics plus the full quantile distribution, which makes the gap visible: a 2025 median of 23.4 months against a mean of 27.3, with a p90 of 47.3. A comparison that puts a US mean beside a Dutch median overstates US duration by roughly two months before anything real is measured. New Zealand does publish medians, but only for the consent-processing phase; its construction figure is a model assumption and is not a median of anything. Austria is the sharpest case: Statistik Austria computes a median construction duration, uses it internally as an imputation parameter, and has never published the value.
This is the largest single distortion in the dataset, and it is concentrated in the developing-country figures. Permit-based statistics only see housing that goes through the permit system. Where most housing does not, the permitting indicator describes a minority of production — and a country can have fast permits precisely because most housing bypasses them.
One caution on the slum-share indicator: it measures housing deprivation (durability, crowding, water, sanitation, tenure), not permit status, so it is a proxy and not a substitute. It also produces artefacts at the top of the income distribution — Ireland registers 8.5%, which is a definitional quirk of overcrowding and tenure measures in a high-income housing system, not a finding about Irish informality.
Verification. This study was put through an adversarial verification pass before publication: every source URL was resolved, ten headline figures were re-derived from the primary files, and every [ESTIMATE] was recomputed. The US, Netherlands, Poland, Germany, Israel and Chile headline figures all reproduced to the decimal, including their mean/median labels and base years. Four things did not survive and have been corrected here rather than quietly dropped: the England 2014 baseline (an earlier pass replaced Lichfields’ published 284 days and 150% with a back-calculation from the report’s own rounded phrase, and called the substitution a verification; the published pair has been restored); an Irish validation-rejection rate of 23% that recomputes to 22%; an Australian townhouse split that did not sum to its own total; and the Japanese private-certifier claim, which needed the counter-case above. Four cited pages are dead or degraded and are flagged as such in the dataset: the Turkish parliamentary transcript host, India’s National Buildings Organisation, one Chilean trade-press page, and a Nigerian finance paper that is 2010 vintage despite a 2025 upload date.
The World Bank's Doing Business “Dealing with Construction Permits” series is the only dataset that ever published a comparable permitting duration across ~190 economies, and it appears in the dataset here for all 38 countries because nothing else covers them all. Three things must always be said with it. It was discontinued in September 2021 and its final data is from May 2019. It measures a two-storey, 1,300.6 m² general-storage warehouse, not a dwelling. And its “time” includes obtaining water and sewerage connections and registering the completed building at the property registry — it is a whole-lifecycle compliance clock, not a permit clock.
On the integrity question, the record is narrower than commonly reported. The WilmerHale investigation named China, Saudi Arabia, the United Arab Emirates and Azerbaijan. Chile does not appear in the report at all. And the manipulated indicators were Starting a Business, Getting Credit and Paying Taxes — construction permits was not among them. The 2019 permit figures can be cited without an integrity asterisk, provided the discontinuation and the warehouse caveat are both disclosed.
Its successor, B-READY, does publish a time in days — but for a five-storey, 1,800 m² commercial office building, and it currently covers only 17 of these 38 economies. Nineteen more arrive in the 2026 edition and two in 2027. Do not place the two side by side as a 2019-to-2025 trend: they measure different buildings with different scopes, and the apparent US movement from 81 to 97 days is an artefact of the instrument.
Why there is no global average in this study, and will not be one. Averaging these numbers would require that they measure the same thing. They do not. The completion event differs (an electricity connection in Ireland, a builder's opinion in Australia, an administrative backstop in New Zealand). The statistic differs (means in six countries, medians in two). The coverage differs (100% of Dutch dwellings, roughly 10% of Lagos housing). And the segments differ so much within countries — Polish self-build takes 2.4× Polish developer housing — that a national average is already a fiction before any cross-country arithmetic begins. A “global average time to build a house” would be a number with no referent.
Most of the missing data is not missing. It is unpublished, and in several cases the agency holding it has already computed it.
Where a figure below is our own derivation rather than a published number, it is marked [ESTIMATE] and the arithmetic is shown in the notes column. Where sources conflict, both are carried in the dataset with a note on which we trust and why. Where a country does not support a segment, the row reads “not available” and names the agency that would hold it. Nothing is interpolated.
183 records covering all 38 scoped countries. 60 of them carry a construction figure and 26 of the 38 countries have one; the remaining rows record what is not published. Every figure carries a source, a direct URL, a data year, an explicit mean-or-median label, a source tier and a confidence rating. Tier 1 is a national statistical agency or building authority; Tier 2 is multilateral; Tier 3 is an industry body or large-sample survey; Tier 4 is journalism, consultancy or a property portal and is labelled weak.
| Country | Segment | P1 | Idle | P2 | P3 | Statistic | Basis | Year | Source | Tier | Conf. | Notes |
|---|
All durations in months unless stated. “Idle” is the gap between the permit being issued and construction starting. Scroll the table sideways for the full record; click a truncated Basis or Notes cell to expand it.
US Census Bureau Survey of Construction · Statistics Canada and CMHC · MHCLG, the Scottish Government, the Welsh Government and DfI Northern Ireland · Lichfields Start to Finish and the Letwin Independent Review of Build Out · CSO Ireland and An Coimisiún Pleanála · INSEE and SDES/Sitadel · Destatis and BBSR · CBS Netherlands (StatLine 86260NED and the 2026 custom decomposition) · SCB, Boverket and Kolada · SSB and DiBK · Danmarks Statistik and KL · Statistics Finland and RAKLI · GUS Poland (Efekty działalności budowlanej) · INE Spain, MIVAU and ASPRIMA · ISTAT and the Dipartimento della Funzione Pubblica · Bundesamt für Statistik, Avenir Suisse and Raiffeisen · Statistik Austria · Australian Bureau of Statistics and Master Builders Australia · Stats NZ and MBIE · Japan MLIT, Aichi Prefecture and JAHB · Statistics Korea and MOLIT · Singapore BCA, URA, HDB and CORENET X · National Bureau of Statistics of China · India MoHUA, PMAY-U and PMAY-G · IBGE and CBIC · INEGI, RUV and SEDATU · Statistics South Africa, the Department of Human Settlements and NHBRC · Dubai Municipality and Dubai Land Department · GASTAT, MOMRAH/Balady and REGA · Nigeria NBS and LASPPPA · KNBS and KPDA · TÜİK · Israel CBS, the Bank of Israel and the State Comptroller · INE Chile, CChC, CNEP and Colliers · INDEC · Vietnam GSO · BPS Indonesia · Philippine Statistics Authority · NSO Thailand and REIC · World Bank Doing Business (discontinued 2021) and B-READY 2025 · OECD Affordable Housing Database · UN-Habitat and the World Bank slum-share series · Eurostat.
Direct URLs for every individual figure are in the dataset’s Source URL column.